top of page
![](https://static.wixstatic.com/media/face78_85428d0e37f044888d9dc6aabc51dddbf000.jpg/v1/fill/w_1920,h_1080,al_c,q_90,enc_avif,quality_auto/face78_85428d0e37f044888d9dc6aabc51dddbf000.jpg)
Easter Seals of Greater Washington D.C.
![SCM-Logo-.png](https://static.wixstatic.com/media/face78_554d9382924c464696dc415751eff225~mv2.png/v1/fill/w_293,h_232,al_c,lg_1,q_85,enc_avif,quality_auto/face78_554d9382924c464696dc415751eff225~mv2.png)
Easter Seals of Greater Washington D.C.
Washington D. C.
Industry: Industrial & Commercial Buildings
-
Non-profit organization.
-
(3) story 48,000 GST building.
-
32,000 GSF Underground parking.
Summary:
-
SCM managed all aspects of the project: meeting State, County and Capital Campaign requirements, including grant writing; making cash flow projections of both donations and expenditures; and procuring permits and approvals on this County-Owned site.
-
SCM led project from groundbreaking stage to completion in 24 months.
-
Construction completed on time and on budget.
Size: 80,000 GSF
Construction Cost: $13.7Million
Architect: WAG Architecture